LWB Mixers and Analyzers Installation

Globaltech was contracted under a design-build agreement to provide and install mixers and water quality analyzers at the Water Treatment Plant (WTP), North Booster Pump Station (NBPS), and South Booster Pump Station (SBPS) for the City of Lake Worth Beach. The project scope includes engineering services for design, permitting, procurement, and preparation of drawings, specifications, work orders, and record documents. Permitting efforts involve coordination with the Palm Beach County Health Department and local building authorities.

Key improvements include the installation of mixers, magnetic drive pumps, recirculation piping, chlorine and monochloramine analyzers, and control panels. Electrical work encompasses modifications to existing panels, installation of new conduits and conductors, and integration of new equipment into the SCADA system. A new aluminum platform will also be installed to support the generator.

The project also includes project management, schedule tracking, site visits, startup support, and the preparation of Operations and Maintenance manuals.

Project Achievements / Benefits

The installation of new mixers and water quality analyzers was successfully completed, improving water treatment efficiency and process monitoring at the WTP, NBPS, and SBPS facilities. The new mixers enhance chemical distribution and water quality within storage tanks, while the chlorine and monochloramine analyzers provide accurate, real-time monitoring for better operational control. Integration of magnetic drive pumps and updated SCADA programming increased system responsiveness and reliability. Electrical and control panel upgrades were completed with minimal disruption to ongoing operations. The project was delivered on time, with all systems meeting performance requirements and regulatory standards.

Vendors

G&G Industrial Services

Rexel

Lazenby & Associates

Kasco Marine

Ryan Herco

Graybar Electric Company

Project Timeframe

1 Year and 4 Months

Completed in June 2025

Change Orders

CO1 - Additional Scope of Work

Project Cost Estimate

$908,429

Client

Michael Suarez

City of Lake Worth Beach

301 College St.

Lake Worth Beach, FL 33460

Phone: (561)-586-1713

Expertise

Analyzers Installation