CSID North Blower Room Blower Replacement

This Design-Build project involved replacing two 200 HP centrifugal blowers in the North Blower Building, as the existing units had reached the end of their useful life. The new blower packages include SCADA-controlled actuated inlet valves, flow-paced blower control adjusted by dissolved oxygen (DO) levels, alarm integration into SCADA, and premium efficiency motors. These blowers now supply air to the aeration basins of Package Plants C and D for biological treatment. Globaltech competitively solicited the blower packages and presented an alternative bid that offered significant savings for the client. The project was grant- funded, and Globaltech managed grant coordination and ensured compliance with the Buy American Act and Davis-Bacon requirements.

Project Achievements / Benefits

Key project highlights include increasing operational efficiency with SCADA-controlled blower systems, saving energy costs through premium efficiency motors, modernizing equipment with new blower packages, and ensuring grant funding and compliance with the Buy American Act and Davis-Bacon requirements.

Project Timeframe

14 Months
Completed June 2023

Project Cost Estimate

$712,369.35

Client

Coral Springs Improvement District
10300 NW 11th Manor Coral Springs, FL 33071
Phone: (954) 753-5841

Expertise

Degasifier