PBC WTP 11 Post Treatment

The City of Boynton Beach contracted Globaltech to provide operational upgrades to post-treatment chemical pumping equipment at PBCWUD’s Water Treatment Plant (WTP) No. 11 in Belle Glade, Florida. The existing equipment had reached the end of its usable lifespan.

The improvements included:

  • Replacement of the sodium hydroxide, corrosion inhibitor, and antiscalant dosing systems

  • Installation of a new double-wall HDPE tank

  • Stainless steel fabricated membrane process building inlet filters

  • Enhancements to the degasifier tower cleaning system

  • A new Deep Injection Well (DIW) compressor and FRP building

  • A new antiscalant transfer station

Electrical upgrades consisted of modifications to existing RIO panels and SCADA logic.

These design enhancements improve safety and operational compliance, with all modifications meeting current regulations, codes, and permitting requirements.

Project Achievements / Benefits

Replacement of aged sodium hydroxide, corrosion inhibitor, and antiscalant dosing systems at PBCWUD WTP 11 and other miscellaneous upgrades.

Project Timeframe

3 years
Completed September 2024

Change Orders

Issued for additional services requested by the owner

Project Cost Estimate

$4,550,780

Client

Krystin Berntsen, P.E.
Director, Engineering Division Palm
Beach County Water Utilities Department
8100 Forest Hill Boulevard
West Palm Beach, FL 33413
(561) 493-6000
[email protected]

Expertise

Design Builder, Post Treatment